Projects in Industriepark Höchst
Gas-turbine plant: building block in sustainable-energy strategy

| Description: | Resource-friendly, high-efficiency plant with two gas turbines |
| that produces steam used for downstream power generation | |
| Investment budget: | € 70 million |
| Start-up: | 2011 |
| Electrical output: | 2 x 45 megawatts |
| Location: | Northern section of Industriepark Höchst |
| Contact: | Michael Müller, Corporate Communication |
| Phone: +49 69 305-7952 | |
| michael.mueller3@infraserv.com |
For more about the gas-turbine plant ...
Climate protection in action: biomethane-upgrading plant

| Description: |
Infraserv Höchst and Mainova build a biomethane-upgrading plant: |
| Raw biogas produced in Infraserv Höchst's biogas plant from biosolids | |
| and organic waste is to be upgraded to pipeline-quality biomethane | |
| and fed into the public network | |
| Investment budget: | € 5 million |
| Start-up: | 2011 |
| Output: | 80,000 megawatt-hours (MWh) of biomethane |
| Location: | West section of Industriepark Höchst |
| Contact: | Michael Müller, Corporate Communication |
| Phone: +49 69 305-7952 | |
| michael.mueller3@infraserv.com |
For more about the biomethane-upgrading plant ...
Ticona transferring production plant to Industriepark Höchst
| Description: | Plant for the Hostaform® engineering plastic |
| Start-up: | 2011 |
| Jobs: | Approx. 300 |
| Location: | Southwest section of Industriepark Höchst |
| Contact: | Constanze Buckow-Wallén, |
| Phone: +49 69 305-7183 | |
| constanze.buckow-wallen@infraserv.com |
For
more about the Ticona
plant ...
Waste-to-energy plant for competitive steam and electricity
| Description: | Replacing fossil fuels such as coal and natural gas with refuse-derived fuel (high-calorific-value fractions of municipal and commercial waste), largest facility of its kind in Germany |
| Investment budget: | Approx. € 300 million |
| Total capacity: | 675,000 t/a |
| Facility start-up: | 2011 |
| New jobs: | Approx. 40 |
| Electrical output: | 70 megawatts; 250 t steam/h |
| Energy-utilization level: | Around 90 % |
| Location: | Southwest section of Industriepark Höchst |
| Operator: | Thermal Conversion Compound Industriepark Höchst GmbH, |
| a subsidiary of Infraserv Höchst | |
| Contact: | Michael Müller, Corporate Communication |
| Phone: +49 69 305-7952 | |
| michael.mueller3@infraserv.com |
Read more about the waste-to-energy power plant in Industriepark Höchst ...